Ajmera Aeon

P51800000789

Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 39 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 23 Jul 2017Due 30 Mar 2023

Past deadline by ~39 months.

  1. Registered with RERA

    23 Jul 2017
  2. Original promised completion

    30 Mar 2023

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 39 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

23 Jul 2017

When the project was registered with RERA.

30 Mar 2023

The deadline committed to at registration.

30 Mar 2023

After all approved extensions.

Handover date, when available.

39 mo overdue38.7 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late.

3 projects2 delayed (67%)100% on time

See Ajmera Realty & Infra India Ltd.'s full track record →

Official records

View this project on the MahaRERA portal

Builder: Ajmera Realty & Infra India Ltd. (NAME:Ajmera Realty & Infra India Ltd.)