Deluxe Apartments
P51800000819
Delivered — but late
This project was completed about 17 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
23 Jul 2017Original promised completion
30 Apr 2021The deadline the builder committed to at registration.
Revised deadline after extensions
30 Sept 2022Pushed back ~17 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
23 Jul 2017
When the project was registered with RERA.
30 Apr 2021
The deadline committed to at registration.
30 Sept 2022
After all approved extensions.
—
Handover date, when available.
17 mo delay17 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Apr 2021 | 30 Sept 2022 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 17 months. Limited history — read the project list before drawing conclusions.
See West Avenue Realtors Private Limited's full track record →