Atlanta Heights (A3) - upto 14th Floor
P51800001079
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
26 Jul 2017Original promised completion
30 Dec 2024The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jun 2026Pushed back ~18 months across 1 extension.
Today — in progress
Deadline is near.
Timeline & delay
Key dates and how they compare to what was promised.
26 Jul 2017
When the project was registered with RERA.
30 Dec 2024
The deadline committed to at registration.
30 Jun 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
51
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2024 | 30 Jun 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 16 projects — 4 delivered, 12 still active. 7 of 16 (44%) ran late by an average of 12 months.
Official records
Builder: Rare Townships Private Limited (NAME:Rare Townships Private Limited)
Data last refreshed 21 Jun 2026.