MAULI OMKAR
P51800001198
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
27 Jul 2017Original promised completion
8 Jul 2023The deadline the builder committed to at registration.
Revised deadline after extensions
7 Jul 2027Pushed back ~48 months across 1 extension.
Today — in progress
About 13 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
27 Jul 2017
When the project was registered with RERA.
8 Jul 2023
The deadline committed to at registration.
7 Jul 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 8 Jul 2023 | 7 Jul 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 3 projects — 0 delivered, 3 still active. 1 of 3 (33%) ran late.
Official records
Builder: MAULI SAI DEVELOPERS PVT LTD (NAME:MAULI SAI DEVELOPERS PVT LTD)
Data last refreshed 21 Jun 2026.