CLARION
P51800001685
Delivered — but late
This project was completed about 29 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
29 Jul 2017Original promised completion
30 Jun 2019The deadline the builder committed to at registration.
Revised deadline after extensions
28 Nov 2021Pushed back ~29 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
29 Jul 2017
When the project was registered with RERA.
30 Jun 2019
The deadline committed to at registration.
28 Nov 2021
After all approved extensions.
—
Handover date, when available.
29 mo delay29 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2019 | 28 Nov 2021 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 6 projects — 3 delivered, 3 still active. 1 of 6 (17%) ran late by an average of 10 months.
Official records
Builder: Sheth Developers Private Limited (NAME:Sheth Developers Private Limited)
Data last refreshed 21 Jun 2026.