MAULI DESIRE
P51800001946
Behind schedule
This project is about 12 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~12 months.
Registered with RERA
29 Jul 2017Original promised completion
31 Jan 2019The deadline the builder committed to at registration.
Revised deadline after extensions
29 Jun 2025Pushed back ~77 months across 1 extension.
Today — still not completed
About 12 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
29 Jul 2017
When the project was registered with RERA.
31 Jan 2019
The deadline committed to at registration.
29 Jun 2025
After all approved extensions.
—
Handover date, when available.
12 mo overdue11.8 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
6
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Jan 2019 | 29 Jun 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 3 projects — 0 delivered, 3 still active. 1 of 3 (33%) ran late.
Official records
Builder: MAULI SAI DEVELOPERS PVT LTD (NAME:MAULI SAI DEVELOPERS PVT LTD)
Data last refreshed 21 Jun 2026.