OM SATYAM NIWAS CHS LTD
P51800002293
Behind schedule
This project is about 47 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~47 months.
Registered with RERA
31 Jul 2017Original promised completion
31 Jul 2020The deadline the builder committed to at registration.
Revised deadline after extensions
31 Jul 2022Pushed back ~24 months across 1 extension.
Today — still not completed
About 47 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
31 Jul 2017
When the project was registered with RERA.
31 Jul 2020
The deadline committed to at registration.
31 Jul 2022
After all approved extensions.
—
Handover date, when available.
47 mo overdue46.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Jul 2020 | 31 Jul 2022 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
See Greenfield Developers & Realtors LLP's full track record →
Official records
Builder: Greenfield Developers & Realtors LLP (NAME:Greenfield Developers & Realtors LLP)
Data last refreshed 21 Jun 2026.