Hubtown Premiere Residences - Tower 3

P51800002977

Mumbai Suburban, MaharashtraResidential / Group HousingIn progress

Under construction

Currently within its planned build window. Watch the deadline and any new extensions.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 4 Aug 2017Due 31 Jul 2029

Within the planned build window.

  1. Registered with RERA

    4 Aug 2017
  2. Original promised completion

    31 Jul 2029

    The deadline the builder committed to at registration.

  3. Today — in progress

    About 37 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

4 Aug 2017

When the project was registered with RERA.

31 Jul 2029

The deadline committed to at registration.

31 Jul 2029

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Mixed track record

Tracking 14 projects — 9 delivered, 5 still active. 4 of 14 (29%) ran late by an average of 6 months.

14 projects4 delayed (29%)56% on time

See Hubtown Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: Hubtown Limited (NAME:Hubtown Limited)

Data last refreshed 21 Jun 2026.