Emerald Isle - T4, T5, T6
RERA project status · delays · complaints · Larsen & Toubro Ltd. (Realty Division)
P51800003307
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
5 Aug 2017Original promised completion
31 Dec 2017The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jun 2018Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
5 Aug 2017
When the project was registered with RERA.
31 Dec 2017
The deadline committed to at registration.
30 Jun 2018
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
18
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2017 | 30 Jun 2018 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 19 projects — 7 delivered, 12 still active. 8 of 19 (42%) ran late by an average of 1 month.
See Larsen & Toubro Ltd. (Realty Division)'s full track record →
Official records
Builder: Larsen & Toubro Ltd. (Realty Division) (NAME:LARSEN TOUBRO LTD REALTY DIVISION)
Data last refreshed 21 Jun 2026.