Athena

P51800003330

Mumbai Suburban, MaharashtraOthersCompleted

Delivered — but late

This project was completed about 46 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 5 Aug 2017Due 31 Jan 2024

Completed.

  1. Registered with RERA

    5 Aug 2017
  2. Original promised completion

    31 Mar 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Jan 2024

    Pushed back ~46 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

5 Aug 2017

When the project was registered with RERA.

31 Mar 2020

The deadline committed to at registration.

31 Jan 2024

After all approved extensions.

Handover date, when available.

46 mo delay46 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Mar 202031 Jan 2024MahaRERA extension (original vs revised completion date)

Official records

View this project on the MahaRERA portal

Data last refreshed 22 Jun 2026.