← Back to search

VISION HEIGHTS WING B

P51800003396

Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 6 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 5 Aug 2017Due 30 Dec 2025

Past deadline by ~6 months.

  1. Registered with RERA

    5 Aug 2017
  2. Original promised completion

    30 Dec 2025

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 6 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

5 Aug 2017

When the project was registered with RERA.

30 Dec 2025

The deadline committed to at registration.

30 Dec 2025

After all approved extensions.

Handover date, when available.

6 mo overdue5.8 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 4 projects — 2 delivered, 2 still active. 4 of 4 (100%) ran late by an average of 24 months.

4 projects4 delayed (100%)0% on time

See FIONA REALTY PRIVATE LIMITED's full track record →

Official records

View this project on the MahaRERA portal

Builder: FIONA REALTY PRIVATE LIMITED (NAME:FIONA REALTY)

Data last refreshed 22 Jun 2026.