← Back to search

OMKAR CHS LTD

P51800003558

Mumbai Suburban, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 12 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 5 Aug 2017Due 30 Jun 2024

Completed.

  1. Registered with RERA

    5 Aug 2017
  2. Original promised completion

    1 Jul 2023

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Jun 2024

    Pushed back ~12 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

5 Aug 2017

When the project was registered with RERA.

1 Jul 2023

The deadline committed to at registration.

30 Jun 2024

After all approved extensions.

Handover date, when available.

12 mo delay12 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
1 Jul 202330 Jun 2024MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 4 projects — 4 delivered, 0 still active. 1 of 4 (25%) ran late by an average of 3 months.

4 projects1 delayed (25%)75% on time

See LAKSHMI BUILDERS AND DEVELOPERS's full track record →

Official records

View this project on the MahaRERA portal

Builder: LAKSHMI BUILDERS AND DEVELOPERS (NAME:LAKSHMI BUILDERS AND DEVELOPERS)

Data last refreshed 21 Jun 2026.