Prem Belaire
P51800003675
Delivered — but late
This project was completed about 65 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
6 Aug 2017Original promised completion
2 Feb 2019The deadline the builder committed to at registration.
Revised deadline after extensions
5 Jul 2024Pushed back ~65 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
6 Aug 2017
When the project was registered with RERA.
2 Feb 2019
The deadline committed to at registration.
5 Jul 2024
After all approved extensions.
—
Handover date, when available.
65 mo delay65.1 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 2 Feb 2019 | 5 Jul 2024 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 65 months. Limited history — read the project list before drawing conclusions.
Official records
Builder: M/s Aryan Infra (NAME:M/s Aryan Infra)
Data last refreshed 21 Jun 2026.