K K RESIDENCY
P51800005115
Behind schedule
This project is about 54 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~54 months.
Registered with RERA
9 Aug 2017Original promised completion
30 Dec 2021The deadline the builder committed to at registration.
Today — still not completed
About 54 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
9 Aug 2017
When the project was registered with RERA.
30 Dec 2021
The deadline committed to at registration.
30 Dec 2021
After all approved extensions.
—
Handover date, when available.
54 mo overdue53.7 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
25
Complaints against the builder
0
Often reported per project on MahaRERA
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: Anis Yakub Khan (NAME:Anis Yakub Khan)
Data last refreshed 21 Jun 2026.