← Back to search

MEDHA CHSL

P51800006437

Mumbai Suburban, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 18 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 14 Aug 2017Due 30 Sept 2020

Completed.

  1. Registered with RERA

    14 Aug 2017
  2. Original promised completion

    31 Mar 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Sept 2020

    Pushed back ~18 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

14 Aug 2017

When the project was registered with RERA.

31 Mar 2019

The deadline committed to at registration.

30 Sept 2020

After all approved extensions.

Handover date, when available.

18 mo delay18 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Mar 201930 Sept 2020MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 5 projects — 5 delivered, 0 still active. 3 of 5 (60%) ran late by an average of 11 months.

5 projects3 delayed (60%)40% on time

See C H PATIL AND SONS LLP's full track record →

Official records

View this project on the MahaRERA portal

Builder: C H PATIL AND SONS LLP (NAME:C H PATIL AND SONS LLP)

Data last refreshed 21 Jun 2026.