SARTHAK HEIGHTS
P51800007127
Delivered — but late
This project was completed about 73 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
17 Aug 2017Original promised completion
30 Nov 2019The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2025Pushed back ~73 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
17 Aug 2017
When the project was registered with RERA.
30 Nov 2019
The deadline committed to at registration.
31 Dec 2025
After all approved extensions.
—
Handover date, when available.
73 mo delay73 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
16
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Nov 2019 | 31 Dec 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 73 months. Limited history — read the project list before drawing conclusions.
Official records
Builder: Sarthak Developers (NAME:Sarthak Developers)
Data last refreshed 21 Jun 2026.