← Back to search

Shree Prafull CHSL

P51800009183

Mumbai Suburban, MaharashtraOthersOverdue

Behind schedule

This project is about 34 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 22 Aug 2017Due 1 Sept 2023

Past deadline by ~34 months.

  1. Registered with RERA

    22 Aug 2017
  2. Original promised completion

    1 Mar 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    1 Sept 2023

    Pushed back ~30 months across 1 extension.

  4. Today — still not completed

    About 34 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

22 Aug 2017

When the project was registered with RERA.

1 Mar 2021

The deadline committed to at registration.

1 Sept 2023

After all approved extensions.

Handover date, when available.

34 mo overdue33.7 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
1 Mar 20211 Sept 2023MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See Shree Shyam Developers's full track record →

Official records

View this project on the MahaRERA portal

Builder: Shree Shyam Developers (NAME:SHREE SHYAM DEVELOPERS)

Data last refreshed 22 Jun 2026.