ATMARAM CHSL
P51800011731
Delivered — but late
This project was completed about 35 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
31 Aug 2017Original promised completion
31 Oct 2019The deadline the builder committed to at registration.
Revised deadline after extensions
30 Sept 2022Pushed back ~35 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
31 Aug 2017
When the project was registered with RERA.
31 Oct 2019
The deadline committed to at registration.
30 Sept 2022
After all approved extensions.
—
Handover date, when available.
35 mo delay35 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Oct 2019 | 30 Sept 2022 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 35 months. Limited history — read the project list before drawing conclusions.
Official records
Builder: NAMOREALTY AND INFRA LLP (NAME:NAMOREALTY AND INFRA)
Data last refreshed 22 Jun 2026.