SHRADDHA ORCHID AVENUE
RERA project status · delays · complaints · SHRADDHA LANDMARK PRIVATE LIMITED
P51800012384
Delivered — but late
This project was completed about 3 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
1 Sept 2017Original promised completion
31 Dec 2017The deadline the builder committed to at registration.
Revised deadline after extensions
10 Apr 2018Pushed back ~3 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
1 Sept 2017
When the project was registered with RERA.
31 Dec 2017
The deadline committed to at registration.
10 Apr 2018
After all approved extensions.
—
Handover date, when available.
3 mo delay3.3 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2017 | 10 Apr 2018 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 20 projects — 11 delivered, 9 still active. 3 of 20 (15%) ran late by an average of 2 months.
Official records
Builder: SHRADDHA LANDMARK PRIVATE LIMITED (NAME:SHRADDHA LANDMARK)
Data last refreshed 21 Jun 2026.