VILAS VAIBHAV CHS
P51800012414
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
1 Sept 2017Original promised completion
27 Oct 2022The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2027Pushed back ~62 months across 1 extension.
Today — in progress
About 18 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
1 Sept 2017
When the project was registered with RERA.
27 Oct 2022
The deadline committed to at registration.
31 Dec 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 27 Oct 2022 | 31 Dec 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.
Official records
Builder: TUVIN CONSTRUCTIONS LLP (NAME:TUVIN CONSTRUCTIONS)
Data last refreshed 22 Jun 2026.