KAILASH RESIDENCY

P51800014738

Mumbai Suburban, MaharashtraOthersIn progress

Under construction

Currently within its planned build window. Watch the deadline and any new extensions.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 26 Dec 2017Due 28 Aug 2026

Approaching the deadline.

  1. Registered with RERA

    26 Dec 2017
  2. Original promised completion

    28 Aug 2022

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    28 Aug 2026

    Pushed back ~48 months across 1 extension.

  4. Today — in progress

    About 2 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

26 Dec 2017

When the project was registered with RERA.

28 Aug 2022

The deadline committed to at registration.

28 Aug 2026

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
28 Aug 202228 Aug 2026MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.

1 projects0 delayed (0%)

See TRIDEV SHREEJI ASSOCIATES's full track record →

Official records

View this project on the MahaRERA portal

Builder: TRIDEV SHREEJI ASSOCIATES (NAME:TRIDEV SHREEJI ASSOCIATES)

Data last refreshed 22 Jun 2026.