Gulab Mansion
P51800015543
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
8 Mar 2018Original promised completion
31 Mar 2020The deadline the builder committed to at registration.
Revised deadline after extensions
31 Aug 2027Pushed back ~89 months across 1 extension.
Today — in progress
About 14 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
8 Mar 2018
When the project was registered with RERA.
31 Mar 2020
The deadline committed to at registration.
31 Aug 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Mar 2020 | 31 Aug 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.
Official records
Builder: Jyotindrakumar Punamchand Shah (NAME:Jyotindrakumar Punamchand Shah)
Data last refreshed 21 Jun 2026.