VISHNU BHASKAR CHS LTD
P51800015748
Delivered — but late
This project was completed about 55 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
22 Mar 2018Original promised completion
10 Sept 2019The deadline the builder committed to at registration.
Revised deadline after extensions
26 Mar 2024Pushed back ~55 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
22 Mar 2018
When the project was registered with RERA.
10 Sept 2019
The deadline committed to at registration.
26 Mar 2024
After all approved extensions.
—
Handover date, when available.
55 mo delay54.5 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 10 Sept 2019 | 26 Mar 2024 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 1 delivered, 3 still active. 3 of 4 (75%) ran late by an average of 55 months.
See SUDHANSHU INFRASTRUCTURES PRIVATE LIMITED's full track record →