← Back to search

SHEETAL VAIBHAV

P51800019010

Mumbai Suburban, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 44 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 28 Dec 2018Due 31 Dec 2025

Completed.

  1. Registered with RERA

    28 Dec 2018
  2. Original promised completion

    1 May 2022

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Dec 2025

    Pushed back ~44 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

28 Dec 2018

When the project was registered with RERA.

1 May 2022

The deadline committed to at registration.

31 Dec 2025

After all approved extensions.

Handover date, when available.

44 mo delay44 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
1 May 202231 Dec 2025MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 1 of 2 (50%) ran late by an average of 44 months. Limited history — read the project list before drawing conclusions.

2 projects1 delayed (50%)0% on time

See D G S TOWNSHIP PRIVATE LIMITED's full track record →

Official records

View this project on the MahaRERA portal

Builder: D G S TOWNSHIP PRIVATE LIMITED (NAME:D G S TOWNSHIP)

Data last refreshed 22 Jun 2026.