The journey from RERA registration to completion, in order.

Registered 12 Feb 2020Due 30 Nov 2026

Approaching the deadline.

  1. Registered with RERA

    12 Feb 2020
  2. Original promised completion

    30 Mar 2024

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Nov 2026

    Pushed back ~32 months across 1 extension.

  4. Today — in progress

    About 5 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

12 Feb 2020

When the project was registered with RERA.

30 Mar 2024

The deadline committed to at registration.

30 Nov 2026

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Mar 202430 Nov 2026MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 2 projects — 0 delivered, 2 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.

2 projects1 delayed (50%)

See VARUN HOMES PVT LTD's full track record →

Official records

View this project on the MahaRERA portal

Builder: VARUN HOMES PVT LTD (NAME:VARUN HOMES)

Data last refreshed 22 Jun 2026.