Pant Nagar Gulmohar Chs Ltd
P51800026241
Behind schedule
This project is about 3 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~3 months.
Registered with RERA
2 Sept 2020Original promised completion
30 Dec 2024The deadline the builder committed to at registration.
Revised deadline after extensions
31 Mar 2026Pushed back ~15 months across 1 extension.
Today — still not completed
About 3 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
2 Sept 2020
When the project was registered with RERA.
30 Dec 2024
The deadline committed to at registration.
31 Mar 2026
After all approved extensions.
—
Handover date, when available.
3 mo overdue2.8 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2024 | 31 Mar 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 2 projects — 1 delivered, 1 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: Pragati Developers (NAME:PRAGATI DEVELOPERS)
Data last refreshed 22 Jun 2026.