BLUE FORTUNA PHASE II
P51800026518
Behind schedule
This project is about 7 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~7 months.
Registered with RERA
30 Sept 2020Original promised completion
30 Sept 2023The deadline the builder committed to at registration.
Revised deadline after extensions
28 Nov 2025Pushed back ~26 months across 1 extension.
Today — still not completed
About 7 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
30 Sept 2020
When the project was registered with RERA.
30 Sept 2023
The deadline committed to at registration.
28 Nov 2025
After all approved extensions.
—
Handover date, when available.
7 mo overdue6.9 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Sept 2023 | 28 Nov 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 3 projects — 2 delivered, 1 still active. 1 of 3 (33%) ran late.
See ATUL PROJECTS INDIA PRIVATE LIMITED's full track record →
Official records
Builder: ATUL PROJECTS INDIA PRIVATE LIMITED (NAME:ATUL PROJECTS INDIA)
Data last refreshed 22 Jun 2026.