Shamim Tower C wing

P51800028222

Mumbai Suburban, MaharashtraOthersOverdue

Behind schedule

This project is about 41 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 15 Feb 2021Due 31 Jan 2023

Past deadline by ~41 months.

  1. Registered with RERA

    15 Feb 2021
  2. Original promised completion

    31 Jan 2023

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 41 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

15 Feb 2021

When the project was registered with RERA.

31 Jan 2023

The deadline committed to at registration.

31 Jan 2023

After all approved extensions.

Handover date, when available.

41 mo overdue40.8 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See Pramod Pisal's full track record →

Official records

View this project on the MahaRERA portal

Builder: Pramod Pisal (NAME:PRAMOD PISAL)

Data last refreshed 22 Jun 2026.