Sumit One

P51800030624

Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 18 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 8 Sept 2021Due 31 Dec 2024

Past deadline by ~18 months.

  1. Registered with RERA

    8 Sept 2021
  2. Original promised completion

    31 Dec 2024

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 18 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

8 Sept 2021

When the project was registered with RERA.

31 Dec 2024

The deadline committed to at registration.

31 Dec 2024

After all approved extensions.

Handover date, when available.

18 mo overdue17.8 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Mixed track record

Tracking 5 projects — 3 delivered, 2 still active. 2 of 5 (40%) ran late by an average of 4 months.

5 projects2 delayed (40%)67% on time

See Sumit Woods Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: Sumit Woods Limited (NAME:SUMIT WOODS)