IORA at L and T Realty Elixir Reserve
RERA project status · delays · complaints · Larsen & Toubro Ltd. (Realty Division)
P51800033984
Behind schedule
This project is about 13 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~14 months.
Registered with RERA
14 Mar 2022Original promised completion
31 May 2025The deadline the builder committed to at registration.
Today — still not completed
About 14 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
14 Mar 2022
When the project was registered with RERA.
31 May 2025
The deadline committed to at registration.
31 May 2025
After all approved extensions.
—
Handover date, when available.
13 mo overdue12.8 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 19 projects — 7 delivered, 12 still active. 8 of 19 (42%) ran late by an average of 1 month.
See Larsen & Toubro Ltd. (Realty Division)'s full track record →
Official records
Builder: Larsen & Toubro Ltd. (Realty Division) (NAME:LARSEN TOUBRO LTD REALTY DIVISION)
Data last refreshed 22 Jun 2026.