← Back to search

NIKUNJ VIHAR CO-OPERATIVE HOUSING SOCIETY LIMITED

P51800047603

Mumbai Suburban, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 1 month after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 14 Nov 2022Due 9 Oct 2024

Completed.

  1. Registered with RERA

    14 Nov 2022
  2. Original promised completion

    31 Aug 2024

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    9 Oct 2024

    Pushed back ~1 month across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

14 Nov 2022

When the project was registered with RERA.

31 Aug 2024

The deadline committed to at registration.

9 Oct 2024

After all approved extensions.

Handover date, when available.

1 mo delay1.3 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Aug 20249 Oct 2024MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 9 projects — 4 delivered, 5 still active. 2 of 9 (22%) ran late by an average of 0 months.

9 projects2 delayed (22%)75% on time

See SAMARPAN HOMES & DEVELOPERS's full track record →

Official records

View this project on the MahaRERA portal

Builder: SAMARPAN HOMES & DEVELOPERS (NAME:SAMARPAN HOMES DEVELOPERS)

Data last refreshed 22 Jun 2026.