ROYALE 22

P51800048541

Mumbai Suburban, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 8 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 6 Jan 2023Due 31 May 2026

Completed.

  1. Registered with RERA

    6 Jan 2023
  2. Original promised completion

    30 Sept 2025

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 May 2026

    Pushed back ~8 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

6 Jan 2023

When the project was registered with RERA.

30 Sept 2025

The deadline committed to at registration.

31 May 2026

After all approved extensions.

Handover date, when available.

8 mo delay8 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Sept 202531 May 2026MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 4 months. Limited history — read the project list before drawing conclusions.

2 projects1 delayed (50%)50% on time

See VS DEVELOPERS's full track record →

Official records

View this project on the MahaRERA portal

Builder: VS DEVELOPERS (NAME:VS DEVELOPERS)

Data last refreshed 22 Jun 2026.