Proposed Bldg on Plot CTS No. 827 B, S.No. 239, in betn Shivneri CHS MCGM Pumphouse, Khadakpada

P51800077357

Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 9 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 9 Aug 2024Due 30 Sept 2025

Past deadline by ~9 months.

  1. Registered with RERA

    9 Aug 2024
  2. Original promised completion

    30 Sept 2025

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 9 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

9 Aug 2024

When the project was registered with RERA.

30 Sept 2025

The deadline committed to at registration.

30 Sept 2025

After all approved extensions.

Handover date, when available.

9 mo overdue8.8 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 12 projects — 7 delivered, 5 still active. 6 of 12 (50%) ran late by an average of 3 months.

12 projects6 delayed (50%)86% on time

See MUMBAI HOUSING AND AREA DEVELOPMENT BOARD's full track record →

Official records

View this project on the MahaRERA portal

Builder: MUMBAI HOUSING AND AREA DEVELOPMENT BOARD (NAME:MUMBAI HOUSING AND AREA DEVELOPMENT BOARD)

Data last refreshed 22 Jun 2026.