NEW CUFFE PARADE - LODHA ENCHANTE
P51900000367
Delivered — but late
This project was completed about 12 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
15 Jul 2017Original promised completion
30 Jun 2018The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jun 2019Pushed back ~12 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
15 Jul 2017
When the project was registered with RERA.
30 Jun 2018
The deadline committed to at registration.
30 Jun 2019
After all approved extensions.
—
Handover date, when available.
12 mo delay12 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
16
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2018 | 30 Jun 2019 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 33 projects — 30 delivered, 3 still active. 6 of 33 (18%) ran late by an average of 3 months.
Official records
Builder: LODHA DEVELOPERS LIMITED (NAME:LODHA DEVELOPERS LIMITED)
Data last refreshed 21 Jun 2026.