RAJHANS
P51900002771
Behind schedule
This project is about 29 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~29 months.
Registered with RERA
4 Aug 2017Original promised completion
31 Dec 2019The deadline the builder committed to at registration.
Revised deadline after extensions
31 Jan 2024Pushed back ~49 months across 1 extension.
Today — still not completed
About 29 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
4 Aug 2017
When the project was registered with RERA.
31 Dec 2019
The deadline committed to at registration.
31 Jan 2024
After all approved extensions.
—
Handover date, when available.
29 mo overdue28.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2019 | 31 Jan 2024 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: PRATHAM DEVELOPERS (NAME:PRATHAM DEVELOPERS)
Data last refreshed 21 Jun 2026.