Metro Grande Tower C and D
P51900004149
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
8 Aug 2017Original promised completion
30 Dec 2024The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jun 2025Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
8 Aug 2017
When the project was registered with RERA.
30 Dec 2024
The deadline committed to at registration.
30 Jun 2025
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2024 | 30 Jun 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 6 months. Limited history — read the project list before drawing conclusions.
See West Pioneer Properties India Pvt Ltd's full track record →
Official records
Builder: West Pioneer Properties India Pvt Ltd (NAME:West Pioneer Properties India Pvt Ltd)
Data last refreshed 21 Jun 2026.