DILKAP GRANDEUR
P51900006119
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
14 Aug 2017Original promised completion
30 Jun 2023The deadline the builder committed to at registration.
Revised deadline after extensions
31 Jul 2026Pushed back ~37 months across 1 extension.
Today — in progress
About 1 month left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
14 Aug 2017
When the project was registered with RERA.
30 Jun 2023
The deadline committed to at registration.
31 Jul 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
11
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2023 | 31 Jul 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 2 projects — 1 delivered, 1 still active. 1 of 2 (50%) ran late by an average of 56 months. Limited history — read the project list before drawing conclusions.
See DILIP ESTATE & TOWN PLANNERS PVT LTD's full track record →
Official records
Builder: DILIP ESTATE & TOWN PLANNERS PVT LTD (NAME:DILIP ESTATE & TOWN PLANNERS PVT LTD)
Data last refreshed 21 Jun 2026.