← Back to search

Waterfront Tower

P51900006784

Mumbai City, MaharashtraResidential / Group HousingCompleted

Delivered on time

Marked completed on the registry on or before the promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 16 Aug 2017Due 31 Jul 2023

Completed.

  1. Registered with RERA

    16 Aug 2017
  2. Original promised completion

    31 Jul 2023

    The deadline the builder committed to at registration.

  3. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

16 Aug 2017

When the project was registered with RERA.

31 Jul 2023

The deadline committed to at registration.

31 Jul 2023

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 1 project — 1 delivered, 0 still active. No delays recorded so far. Limited history — read the project list before drawing conclusions.

1 projects0 delayed (0%)100% on time

See Sea Kunal Corporation Pvt. Ltd.'s full track record →

Official records

View this project on the MahaRERA portal

Builder: Sea Kunal Corporation Pvt. Ltd. (NAME:Sea Kunal Corporation Pvt. Ltd.)

Data last refreshed 21 Jun 2026.