Construction of Mill Workers Tenements at Shrinivas MIll Lower Parel

P51900007421

Mumbai City, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 30 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 17 Aug 2017Due 30 Dec 2023

Past deadline by ~30 months.

  1. Registered with RERA

    17 Aug 2017
  2. Original promised completion

    31 Dec 2018

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Dec 2023

    Pushed back ~60 months across 1 extension.

  4. Today — still not completed

    About 30 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

17 Aug 2017

When the project was registered with RERA.

31 Dec 2018

The deadline committed to at registration.

30 Dec 2023

After all approved extensions.

Handover date, when available.

30 mo overdue29.7 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 201830 Dec 2023MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 15 projects — 10 delivered, 5 still active. 9 of 15 (60%) ran late by an average of 16 months.

15 projects9 delayed (60%)60% on time

See MHADA's full track record →

Official records

View this project on the MahaRERA portal

Builder: MHADA (NAME:MHADA)

Data last refreshed 21 Jun 2026.