THE WORLD TOWERS - WORLD ONE - TIER II
P51900008345
Delivered — but late
This project was completed about 17 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
18 Aug 2017Original promised completion
30 Sept 2018The deadline the builder committed to at registration.
Revised deadline after extensions
25 Feb 2020Pushed back ~17 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
18 Aug 2017
When the project was registered with RERA.
30 Sept 2018
The deadline committed to at registration.
25 Feb 2020
After all approved extensions.
—
Handover date, when available.
17 mo delay16.9 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
15
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Sept 2018 | 25 Feb 2020 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 5 projects — 5 delivered, 0 still active. 1 of 5 (20%) ran late by an average of 3 months.
Official records
Builder: MACROTECH DEVELOPERS LIMITED (NAME:MACROTECH DEVELOPERS LIMITED)
Data last refreshed 21 Jun 2026.