LE PALAZZO
P51900012304
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
1 Sept 2017Original promised completion
30 Apr 2019The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
1 Sept 2017
When the project was registered with RERA.
30 Apr 2019
The deadline committed to at registration.
30 Apr 2019
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
22
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Apr 2019 | 31 Aug 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 1 delivered, 0 still active. No delays recorded so far. Limited history — read the project list before drawing conclusions.