BKC EDGE

P51900013846

Mumbai City, MaharashtraCommercialOverdue

Behind schedule

This project is about 27 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 27 Oct 2017Due 30 Mar 2024

Past deadline by ~27 months.

  1. Registered with RERA

    27 Oct 2017
  2. Original promised completion

    30 Mar 2024

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 27 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

27 Oct 2017

When the project was registered with RERA.

30 Mar 2024

The deadline committed to at registration.

30 Mar 2024

After all approved extensions.

Handover date, when available.

27 mo overdue26.7 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

3

Complaints against the builder

0

Often reported per project on MahaRERA

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Mar 202431 Dec 2029MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See Labdhi Bliss Private Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: Labdhi Bliss Private Limited (NAME:Labdhi Bliss Private Limited)

Data last refreshed 21 Jun 2026.