One Lodha Place
P51900014984
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
15 Jan 2018Original promised completion
30 Mar 2023The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
15 Jan 2018
When the project was registered with RERA.
30 Mar 2023
The deadline committed to at registration.
30 Mar 2023
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
3
Complaints against the builder
0
Often reported per project on MahaRERA
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 5 projects — 5 delivered, 0 still active. 1 of 5 (20%) ran late by an average of 3 months.
Official records
Builder: MACROTECH DEVELOPERS LIMITED (NAME:MACROTECH DEVELOPERS LIMITED)
Data last refreshed 21 Jun 2026.