Hubtown Harmony A Wing

P51900017558

Mumbai City, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 18 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 28 Aug 2018Due 30 Dec 2024

Past deadline by ~18 months.

  1. Registered with RERA

    28 Aug 2018
  2. Original promised completion

    30 Dec 2024

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 18 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

28 Aug 2018

When the project was registered with RERA.

30 Dec 2024

The deadline committed to at registration.

30 Dec 2024

After all approved extensions.

Handover date, when available.

18 mo overdue17.7 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

1

Complaints against the builder

0

Often reported per project on MahaRERA

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 4 projects — 1 delivered, 3 still active. 3 of 4 (75%) ran late.

4 projects3 delayed (75%)100% on time

See Heet Builders Private Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: Heet Builders Private Limited (NAME:Heet Builders Private Limited)

Data last refreshed 21 Jun 2026.