Shankheshwar Heights
P51900018161
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
11 Oct 2018Original promised completion
30 Jun 2026The deadline the builder committed to at registration.
Today — in progress
Deadline is near.
Timeline & delay
Key dates and how they compare to what was promised.
11 Oct 2018
When the project was registered with RERA.
30 Jun 2026
The deadline committed to at registration.
30 Jun 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2026 | 30 Jun 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.
Official records
Builder: Siddheshwar Construction Co. (NAME:Siddheshwar Construction Co.)
Data last refreshed 21 Jun 2026.