Siddha Sky Phase 3
P51900021044
Behind schedule
This project is about 1 month past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~1 month.
Registered with RERA
31 May 2019Original promised completion
30 May 2026The deadline the builder committed to at registration.
Today — still not completed
About 1 month past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
31 May 2019
When the project was registered with RERA.
30 May 2026
The deadline committed to at registration.
30 May 2026
After all approved extensions.
—
Handover date, when available.
1 mo overdue0.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
4
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 May 2026 | 31 Dec 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: M/s. Sejal Shakti Realtors LLP (NAME:M/s. Sejal Shakti Realtors LLP)
Data last refreshed 21 Jun 2026.