Completed.
Registered with RERA
31 May 2019Original promised completion
30 Sept 2023The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
31 May 2019
When the project was registered with RERA.
30 Sept 2023
The deadline committed to at registration.
30 Sept 2023
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 1 delivered, 0 still active. No delays recorded so far. Limited history — read the project list before drawing conclusions.
See JOHAAN REALTORS AND DEVELOPERS PRIVATE LIMITED's full track record →
Official records
Builder: JOHAAN REALTORS AND DEVELOPERS PRIVATE LIMITED (NAME:JOHAAN REALTORS AND DEVELOPERS PRIVATE LIMITED)