HARSH VISTA

P51900024022

Mumbai City, MaharashtraResidential / Group HousingCompleted

Delivered on time

Marked completed on the registry on or before the promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 14 Jan 2020Due 30 Jun 2024

Completed.

  1. Registered with RERA

    14 Jan 2020
  2. Original promised completion

    30 Jun 2024

    The deadline the builder committed to at registration.

  3. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

14 Jan 2020

When the project was registered with RERA.

30 Jun 2024

The deadline committed to at registration.

30 Jun 2024

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

1

Complaints against the builder

0

Often reported per project on MahaRERA

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 2 projects — 2 delivered, 0 still active. No delays recorded so far. Limited history — read the project list before drawing conclusions.

2 projects0 delayed (0%)100% on time

See HARSH DEVELOPERS & INFRASTRUCTURE LLP's full track record →

Official records

View this project on the MahaRERA portal

Builder: HARSH DEVELOPERS & INFRASTRUCTURE LLP (NAME:HARSH DEVELOPERS & INFRASTRUCTURE LLP)

Data last refreshed 21 Jun 2026.