← Back to search

DOSTI EASTERN BAY- PHASE 2

P51900030769

Mumbai City, MaharashtraResidential / Group HousingCompleted

Delivered on time

Marked completed on the registry on or before the promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 13 Sept 2021Due 30 Sept 2027

Completed.

  1. Registered with RERA

    13 Sept 2021
  2. Original promised completion

    30 Sept 2027

    The deadline the builder committed to at registration.

  3. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

13 Sept 2021

When the project was registered with RERA.

30 Sept 2027

The deadline committed to at registration.

30 Sept 2027

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 4 projects — 3 delivered, 1 still active. No delays recorded so far.

4 projects0 delayed (0%)100% on time

See DOSTI REALTY LTD's full track record →

Official records

View this project on the MahaRERA portal

Builder: DOSTI REALTY LTD (NAME:DOSTI REALTY LTD)

Data last refreshed 21 Jun 2026.