Ruparel Millennia
P51900031698
Behind schedule
This project is about 6 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~6 months.
Registered with RERA
8 Nov 2021Original promised completion
31 Dec 2025The deadline the builder committed to at registration.
Today — still not completed
About 6 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
8 Nov 2021
When the project was registered with RERA.
31 Dec 2025
The deadline committed to at registration.
31 Dec 2025
After all approved extensions.
—
Handover date, when available.
6 mo overdue5.7 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
3
Complaints against the builder
0
Often reported per project on MahaRERA
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 2 projects — 0 delivered, 2 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.